Thursday, July 17, 2014

Solar panels


This week Joe and I set up the posts for the solar panels and Brett Carter installed the panels. We also spent a day with the electrician installing lights, with the plumber installing the hot water system, with Caleb completing the roof flashing and another installing surfeits. We completed painting last week.









Sunday, July 6, 2014

Painting and tiling

Painting is nearly done now and half the floor is tiled.










Wednesday, June 18, 2014

Latest photos


Plastering is finished, all the windows and doors are in. Next is painting then tiling.




Monday, June 9, 2014

Lockup


We have finally reached lockup stage - all doors and windows are in. That means cold winds and the possums are out. The main roof facia and guttering are also complete thanks to Caleb's tin-smithing artistry.


Glen and Cathy Hanson of Eurotrend Doors and Windows install our final door - a large Lift and Slide door from the living area out to the eastern lawn.

The final door in place.

Wednesday, May 21, 2014

Now the windows are in and the internal framing complete


Joe grinding the concrete slab for tiling. 

Mal's ute as mobile scaffold. 

Morning sun in the bedroom windows




The bedroom, bathroom etc framing. That's all the internal framing apart from the pantry.

Bathroom

Kitchen and pantry


Sunday, April 27, 2014

Final roof goes on as winter sets in.


Hey! Joe came home and is helping us finish our house. How about that! Easter was wet and windy, so was Anzac weekend. But Caleb, Joe Michael and I eventually got the final roof on.









We also installed 6 more Spotted Gum windows and the first  5 clearstory windows.

Malcolm's ute has no end of important uses. A mobile scaffold is one of them.
I probably won't bring it inside once the floor is tiled.